Gray Summit Water Main Replacement / Tucker Hill Lane
The scope of work includes the construction of approximately 1,540 feet of 10-inch diameter PVC water main, associated valves, fittings and other incidental items.

  • Project Construction Start: April 2021
  • Project Construction Completion: June 2021

Tara Place and Lakewood Estates Treatment Consolidation to Lakewood Mobile Home Park Lagoon

The scope of work includes consolidation of the Tara Place WWTP and Lakewood Estates Sandfilter for regional treatment at the Lakewood Mobile Home Park Lagoon.

  • Project Construction Start: Winter 2021
  • Project Construction Completion: June 2021

Gray Summit Water Tank Recoating Project
The scope of work includes minor repair, painting, disinfection, and other incidental items.

  • Project Construction Start: April 2021
  • Project Construction Completion: June 2021