Completed Projects

 

St. Louis Rock Road - Water Main Improvement Project

The scope of work included: construction of approximately 252 lineal feet of 6-inch diameter PVC water main, including 125 lineal feet of steel encasement under St. Louis Rock Road, open-cut and repair of St. Louis Rock Road, approximately 127 lineal feet of open trench installation of 6-inch water main, associated valves, fittings, hardware and other incidental items.

  • Project Completed: July 2019 

 

Office Water Tower Recoating Project
The scope of work included: minor repair, painting, disinfection, add alternate for fill line and other incidental items. The mixing system will improve water turnover in the tank and improve water quality.

  • Projected Completed: June 2019

 

I-44 Water Main Bore Improvement Project
The project interconnected water mains from both sides of Interstate 44 and eliminated several dead-end water mains within the District. The Scope of Work included: construction of approximately 944 lineal feet of 12-inch diameter PVC water main, including 240 lineal feet of bore and steel encasement under Interstate 44, 125 lineal feet of bore and steel encasement under Highway 100, pressure reducing valve and structure and approximately 580 lineal feet of open trench installation of 12-inch PVC water main.

  • Project Completed: April 2019

 

Lake Serene Water Main Improvement Project
The scope of work includes: construction of approximately 16,800 lineal feet of new water main to replace existing aging pipe within the Lake Serene corridor. Water main replacement will occur along all, or a portion of, North Shore Dr., Box Elder Dr., Cedar St., Ash St., South Shore Dr., Sunset Dr., Cherry Ln., Paw Paw St., Lake View Dr., and Cedar Brook Ln.

  • Projected Completed: September 2019