Completed Projects

 

Highway T / Labadie Creek Crossing -- Water Main Improvements
The scope of work includes: construction of approximately 1,308 lineal feet of 8-inch diameter water main, including approximately 55 lineal feet of bore and steel encasement under State Highway T, approximately 366 lineal feet of open-trench installation of 8-inch D.I.P. in creek crossings, approximately 100 lineal feet of directional bore installation of 8-inch PVC under existing parking area, approximately 787 lineal feet of open trench installation of 8-inch PVC water main, associated valves, fittings, hardware, and other incidental items.

  • Project Completed: January 2020

Victoria Gardens WWTF Single Pass Sand Filter
The scope of work includes: demolition and removal of an existing sand filter and associated piping, construction of a new concrete sand filter structure, installation of filter media and piping, new chlorine tablet feeder, associated valves and piping, relocating & installing new fencing, site grading, finish grading, seeding/mulching, and other incidental items.

  • Project Completed: December 2019

Lakewood Lagoon Repairs (South Cell)
The scope of work includes: earthwork along slope of lagoon cell, placement of a rip-rap apron around entire berm of lagoon, import fill to raise berm, and other incidental items.

  • Project Completed: October 2019

Lake Serene Water Main Replacement Project
The scope of work includes: construction of approximately 16,800 lineal feet of new water main to replace existing aging pipe within the Lake Serene corridor. Water main replacement will occur along all, or a portion of, North Shore Dr., Box Elder Dr., Cedar St., Ash St., South Shore Dr., Sunset Dr., Cherry Ln., Paw Paw St., Lake View Dr., and Cedar Brook Ln.

  • Project Completed: September 2019

St. Louis Rock Road - Water Main Improvement Project

The scope of work included: construction of approximately 252 lineal feet of 6-inch diameter PVC water main, including 125 lineal feet of steel encasement under St. Louis Rock Road, open-cut and repair of St. Louis Rock Road, approximately 127 lineal feet of open trench installation of 6-inch water main, associated valves, fittings, hardware and other incidental items.

  • Project Completed: July 2019 

Office Water Tower Recoating Project
The scope of work included: minor repair, painting, disinfection, add alternate for fill line and other incidental items. The mixing system will improve water turnover in the tank and improve water quality.

  • Project Completed: June 2019

I-44 Water Main Bore Improvement Project
The project interconnected water mains from both sides of Interstate 44 and eliminated several dead-end water mains within the District. The Scope of Work included: construction of approximately 944 lineal feet of 12-inch diameter PVC water main, including 240 lineal feet of bore and steel encasement under Interstate 44, 125 lineal feet of bore and steel encasement under Highway 100, pressure reducing valve and structure and approximately 580 lineal feet of open trench installation of 12-inch PVC water main.

  • Project Completed: April 2019